The CB&I, Michael Baker International and Gannett Fleming joint venture team has announced the completion of construction management services for four projects as part of the six year upgrade of the Newtown Creek Wastewater Treatment Plant in Brooklyn, New York. Not only were the four construction projects, valued at approximately US$1.3 billion, delivered under budget, the team achieved all consent order milestones, allowing US$71.7 million to be returned to the city. The project also was recognised by the American Council of Engineering Companies (ACEC) New York Engineering Excellence Awards, earning Michael Baker and partners the association's 2017 ACEC New York Diamond Award in the category of waste and storm water.

Located on a 53 acre site, the Newtown Creek Plant is the largest of the 14 wastewater treatment facilities inside New York City (NYC). Owned and operated by the NYC Department of Environmental Protection (NYCDEP), the facility processes wastewater from a collective area of approximately 25 miles2 from sections of Brooklyn, Queens and a third of Manhattan.

"Michael Baker is proud to be a part of a partnership that rallied its collective expertise to problem solve and develop innovative and cost effective solutions for the community serviced by this facility," said Michael Brescia, P.E., Michael Baker Senior Vice President and Northeast Regional Director. "As a leader in the field of water resources engineering, these are some of the ways We Make a Difference through our commitment to excellence during all phases of project work."

CB&I, Michael Baker and Gannet Fleming formed the joint venture team for construction management services as part of the final phase of the three-phase upgrade that increased the plant's wet weather processing capacity from 310 - 720 million gal./d. Services consisted of four major construction projects: 1) Construction of Central Residuals Building (CRB), where all non-biological matter is removed from the wastewater; 2) Upgrade of South Battery and Control Building, which provides grit removal, aerobic processing and biological settling for one third of the plant's wastewater flow; 3) Construction of New Sludge Loading Dock facility (on Whale Creek), maintenance dredging of a Superfund site, demolition of the old East River Sludge Storage Tank and decommissioning of the East River Loading Dock; and 4. Construction of miscellaneous other features, various mechanical system modifications and process wrap-up.

Innovation played a key role enabling the construction management team to deliver the project with only a 1.2% change order rate, on time and under budget. The team incorporated 4D Building Information Modelling (BIM) to address construction challenges, meet milestones and finish the projects two months ahead of schedule. Also included in the upgrade, under a separate prior contract with CB&I, was the construction of eight, stainless-steel-clad, egg-shaped, anaerobic digesters designed to reduce landfill gas emissions. These 140 ft high domes are sculpturally lit by blue LED lighting and are visible from numerous Brooklyn, Queens and Manhattan vantage points.

Read the article online at: https://www.hydrocarbonengineering.com/refining/27012017/jv-completes-construction-management-services/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Downstream news North America downstream news