Nacero selects Bechtel for LNG FEED contract

Published by , Editorial Assistant
Hydrocarbon Engineering,


Nacero has selected Bechtel for t the Front-End Engineering and Design (FEED) contract for its natural gas-to-gasoline manufacturing facility in the US.

Nacero's 115 000 bpd gasoline manufacturing plant in Penwell, Texas, near Odessa in the heart of the Permian basin, will incorporate carbon capture, carbon sequestration, and 100% renewable power.

The use of renewable natural gas and mitigated flare gas will make it possible to reduce the lifecycle footprint of Nacero's cost-competitive, zero sulfur gasoline to zero over time. Nacero's products will be sold to retailers in Texas and the Southwest, and through Nacero-branded outlets.

"We are thrilled to partner with Bechtel for our flagship facility in Penwell. Bechtel's experience with large-scale projects and commitment to excellence is second to none," said Jay McKenna, Nacero's President and CEO. "For America to achieve its domestic energy and climate change mitigation goals we need big vision and laser-focused execution. Bechtel is centre stage in helping us get there."

"We are delighted by this opportunity to support Nacero's pioneering approach to delivering lower carbon fuel with our record of large-scale project success," said Paul Marsden, President, Bechtel Energy. "This project is truly a game-changer. It will give every day American drivers a chance to participate in the energy transition and will be a model for the kind of environmental improvement America is looking to bring about."

On completion of the FEED, Bechtel will deliver a lump sum, turnkey EPC price proposal. Bechtel will employ its range of sustainable design and execution tools to bring about carbon reduction in the supply chain and reduce the carbon footprint of the project during construction. Bechtel and Nacero have a shared commitment to best in class environmental, social, and governance (ESG) practices.

The project is expected to employ 3500 skilled construction workers on site at peak during the four years first phase construction. The second phase of construction will take an additional two years and bring plant capacity to 115 000 bpd. When fully operational, the plant will employ 350 full-time operators and maintenance personnel. The University of Texas has estimated that the Penwell facility will add more than US$25 billion to the economy of the Odessa region during its 50+ year operating life.

Read the article online at: https://www.hydrocarbonengineering.com/gas-processing/26052021/nacero-selects-bechtel-for-lng-feed-contract/

You might also like

API releases statement on NPC studies

The American Petroleum Institute (API) has released a statement on the National Petroleum Council (NPC)’s reports on Greenhouse Gas Emissions and Hydrogen.

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Downstream news US refinery news Downstream contract news Biofuel news