Pointe LNG LLC has asked the Federal Energy Regulatory Commission (FERC) to initiate pre-filing review for the Pointe’s proposed LNG liquefaction and export facility to be located in Plaquemines Parish, Louisiana, US.
The facility is to have an initial export capacity of 6 million tpy and will be designed using three 2 million tpy modular trains provided by CHART's IPSMR®+ LNG liquefaction technology. In 2014, a significant portion of the site was previously reviewed by FERC in connection with a previously proposed LNG export terminal project.
Assuming that various contingencies are satisfied, including Pointe LNG's receipt of financing and all necessary permits and approvals, such that it reaches a final investment decision, construction is expected to begin in 1Q21 with initial operations expected in 1Q25.
Read the article online at: https://www.hydrocarbonengineering.com/gas-processing/25092018/pointe-lng-requests-ferc-pre-file-review-for-louisiana-lng-export-facility/
You might also like
Low US distillate consumption reflects slow economic activity and biofuel substitution
The EIA reports that US distillate consumption so far this year is lower than usual because of warm winter weather, reduced manufacturing activity, and continued substitution of biofuels in place of petroleum distillate on the US West Coast (PADD 5).