Freeport LNG and PHMSA enter into Consent Agreement

Published by , Senior Editor
Hydrocarbon Engineering,


Freeport LNG Development L.P. and the Pipeline Hazardous Materials Safety Administration (PHMSA) have en-tered into a Consent Agreement related to the 8 June 2022 incident at Freeport LNG's liquefaction facility.

The obligations under the Consent Agreement are intended to ensure that Freeport LNG can safely and confidently resume initial LNG production and thereafter ultimately return to full operation of all liquefaction facilities.

In the near term, the Consent Agreement includes certain corrective measures, many of which are currently underway, that Freeport LNG is to take to obtain PHMSA approval for an initial resumption of LNG production from its liquefaction facility.

In a statement, Freeport LNG said that it continues to believe that it can complete the necessary corrective measures, along with the applicable repair and restoration activities, in order to resume initial operations in early October. Those initial operations are expected to consist of three liquefaction trains, two LNG storage tanks and one LNG loading dock, which the company believes will enable delivery of approximately 2 billion ft3/d of LNG, enough to support its existing long-term customer agreements.

In addition to the repair and replacement of Freeport LNG's physical infrastructure that was damaged in the incident, and as part of the corrective measures under the Consent Agreement, the company is evaluating and advancing initiatives related to training, process safety management, operations and maintenance procedure improvements, and facility inspections.

Read the article online at: https://www.hydrocarbonengineering.com/gas-processing/04082022/freeport-lng-and-phmsa-enter-into-consent-agreement/

You might also like

The Hydrocarbon Engineering Podcast - Education and training for every phase of the insulating system design process

In this episode of the Hydrocarbon Engineering Podcast, Brandon Stambaugh, Owens Corning Director for Technical Services, joins us to discuss engineers’ demand for education and training to support the critical phases that affect the performance and longevity of insulating systems.

Tune in to the Hydrocarbon Engineering Podcast on your favourite podcast app today.

Apple Podcasts  Spotify Podcasts  YouTube

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Downstream news