Sempra Energy receives FERC notice of schedule for Port Arthur, Texas, LNG export project

Published by , Deputy Editor
Hydrocarbon Engineering,


Sempra Energy, has received a Notice of Schedule from the Federal Energy Regulatory Commission (FERC) that sets 31 January, 2019, as the planned completion date of the final environmental impact statement for siting, construction and operation of the proposed Port Arthur LNG natural gas liquefaction-export project in Jefferson County, Texas.  

"This is an important step forward in the federal regulatory review to construct our Port Arthur liquefaction-export project on Texas' Gulf Coast," said Joseph A. Householder, president and chief operating officer of Sempra Energy. "Federal and Texas state policymakers have been instrumental in supporting US liquefied natural gas (LNG) exports to bolster the US economy."  

"Sempra Energy's new liquefaction facility will be a boon to the Port Arthur community and to the entire state of Texas," said Texas Gov. Greg Abbott. "This project will not only create thousands of jobs and benefit the local economies, but it will also be a boost to our nation's economy. I thank Sempra Energy for their investment in Texas and Port Arthur, and I look forward to the completion of this project."

"I am honoured to have worked to make the Port Arthur LNG export project a reality, which will bring thousands of jobs to Texas and renewed prosperity to communities like Port Arthur, where families are still rebuilding one year after the devastation of Hurricane Harvey," U.S. Sen. Ted Cruz said. "Our Gulf communities remain strong, and Texas continues to forge ahead as an energy leader for America and the entire world."

"Southeast Texas is America's energy gateway," said US Rep. Randy Weber. "As more LNG facilities come online, the contributions our region makes to America's energy dominance further increase. I am grateful to FERC for finalising the notice of schedule, allowing Sempra Energy to complete this project years in the making."

The FERC issued its Notice of Schedule for the proposed Port Arthur liquefaction-export project 31 August. The project is expected to include two natural gas liquefaction trains to enable the long-term sale of approximately 11 million tpy of LNG; feed gas pre-treatment facilities; natural gas liquids and refrigerant storage; up to three LNG storage tanks; two marine berths and associated facilities. 

The ultimate decision to construct the Port Arthur liquefaction project is contingent upon obtaining binding customer commitments and financing arrangements; reaching a definitive engineering, procurement and construction contract; securing all necessary permits and approvals including a FERC order approving the siting, construction and operation of the project and reaching a final investment decision.

Sempra Energy, a San Diego-based energy services holding company with 2017 revenues of more than US$11 billion, is the utility holding company with the largest US customer base. The Sempra Energy companies' approximately 20 000 employees serve more than 40 million consumers worldwide.

Read the article online at: https://www.hydrocarbonengineering.com/tanks-terminals/05092018/sempra-energy-receives-ferc-notice-of-schedule-for-port-arthur-texas-lng-export-project/