Suncor update on Syncrude's Mildred Lake facility
Published by Francesca Brindle,
Editorial Assistant
Hydrocarbon Engineering,
Suncor Energy has provided an update on the Syncrude Mildred Lake oilsands facility following the incident on 14 March.
Repairs are progressing as planned and the maintenance work scheduled for the fall has been added to the plan, extending the timing of full ramp up to mid-July. Shipments have been reduced to approximately 130 000 bpd (gross) in order to complete the accelerated maintenance and are expected to ramp up as additional units complete turnaround activities.
The cause of the incident was a split in a 6 in. carbon steel line on a naphtha hydrotreater recycle circuit. Damage was largely isolated to a piperack adjacent to the hydrotreater, containing piping, cables, and electrical circuits. The maintenance brought forward was included in Syncrude's 2017 production plan, and there is no change to Suncor's overall production guidance for 2017.
Read the article online at: https://www.hydrocarbonengineering.com/refining/14062017/suncor-update-on-syncrudes-mildred-lake-facility/
You might also like
Hydrocarbon Engineering Podcast
Mike Logue, Owens Corning Global Business Director – Mechanical Insulation, delves into factors that can support the performance, safety and longevity of insulating systems installed in hydrocarbon processing environments, including cryogenic facilities.
LBC Rotterdam completes construction of 36 storage tanks
LBC Rotterdam have announced the completion and the arrival of all 36 new storage tanks.