Suncor Energy has provided an update on the Syncrude Mildred Lake oilsands facility following the incident on 14 March.
Repairs are progressing as planned and the maintenance work scheduled for the fall has been added to the plan, extending the timing of full ramp up to mid-July. Shipments have been reduced to approximately 130 000 bpd (gross) in order to complete the accelerated maintenance and are expected to ramp up as additional units complete turnaround activities.
The cause of the incident was a split in a 6 in. carbon steel line on a naphtha hydrotreater recycle circuit. Damage was largely isolated to a piperack adjacent to the hydrotreater, containing piping, cables, and electrical circuits. The maintenance brought forward was included in Syncrude's 2017 production plan, and there is no change to Suncor's overall production guidance for 2017.
Read the article online at: https://www.hydrocarbonengineering.com/refining/14062017/suncor-update-on-syncrudes-mildred-lake-facility/
You might also like
The Hydrocarbon Engineering Podcast - Education and training for every phase of the insulating system design process
In this episode of the Hydrocarbon Engineering Podcast, Brandon Stambaugh, Owens Corning Director for Technical Services, joins us to discuss engineers’ demand for education and training to support the critical phases that affect the performance and longevity of insulating systems.
Tune in to the Hydrocarbon Engineering Podcast on your favourite podcast app today.