BG Group ships first LNG from QCLNG Train 2

 

Published by
Hydrocarbon Engineering,

BG Group plc has started up and loaded its first LNG from the second production train at the Queensland Curtis LNG (QCLNG) facility in Australia. The first LNG from Train 2 set sail on the Maran Gas Posidonia.

At plateau production, expected in mid 2016, both trains at QCLNG will be producing enough LNG to load 10 vessels per month combined, exporting around 8 million tpy. Since production from the first train commenced in December 2014, 27 cargoes have been shipped.

BG Group began commercial operations in May 2015, when control of Train 1 formally transferred to QGC, BG Group's Australian subsidiary, from the constructor Bechtel Australia. Train 2 commercial operations will begin once a similar commissioning process has been completed.

"The start up of QCLNG's second LNG train is another important operational milestone delivered in line with our plan,” said Helge Lund, Chief Executive of BG Group. “The completion of our upstream infrastructure and the two LNG trains are achievements of which BG Group, particularly our team in Australia, can be proud. We have already shipped more than 1.5 million t of LNG from Queensland, and Train 2 will add significant further volumes and flexibility to our LNG shipping and marketing portfolio."


Adapted from press release by Rosalie Starling